| NEW ALLEGHENY HOMEOWNER ASSOCIATION | |
| Capital Improvements Plan 2006-2010 |
Garage
Door Replacement Program:
Program Description: Existing Masonite garage doors will be removed and replaced with white, raised panel, steel garage doors, no windows.
|
2006
Program
Schedule:
# of Homes - Carpenter Lane
9 - Brighton Woods Road – Lower 9 - Lamplighter Circle
10 - Chandler Place
10 - Peddler Place
4 Total 42 |
2007 Program Schedule: # of Homes - Squire Circle
13
- Cobbler Circle
12
- Brighton Woods Road - Upper
5
- Bookbinder
Circle
11 Total 41
|
Road/Driveways
Refurbishing:
Program Description: Existing loose gravel will be removed down to tar/chip surface. Low areas will be filled and a 1-1/2" wearing surface of asphalt will be applied to all driveways, roadways and visitor parking areas.
| 2008
Program Schedule: # of Homes - Brighton Woods Rd – Upper 5 - Bookbinder Circle
11 - Carpenter Lane _9 Total 25 |
2009
Program Schedule: # of Homes - Brighton Woods Rd - Lower
9 - Lamplighter Circle
10 - Chandler Place
10 Total 29 |
2010
Program Schedule: # of Homes - Squire Circle
13 - Peddler Place
4 - Cobbler Circle
12 Total 29 |